Harbour Bakery
Your projects
- 3 active projects
- Needs attention: 1
- Healthy: 2
- 3 decisions needed from you
Wholesale order intake
HealthyOn track to finish 1 Dec 2026, 10 days early, and under the SOW estimate.
1 decision needed from you
Time elapsed57%Work done64%SOW spent50%10 days aheadDue 11 Dec 2026
Stock reordering
Needs attentionForecast to finish 4 Dec 2026, 7 days late, and about 4% over the SOW estimate.
1 decision needed from you
Time elapsed71%Work done67%SOW spent69%7 days behindDue 27 Nov 2026
Customer follow-ups
HealthyToo early to forecast the finish, with 6% of the SOW estimate spent so far.
1 decision needed from you
Time elapsed6%Work done0%SOW spent6%Too early to forecastDue 26 Feb 2027