Show report
As of 30 Oct 2026
Harbour Bakery
Wholesale order intake
HealthyOn track to finish 1 Dec 2026, 10 days early, and under the SOW estimate.
An agent that reads wholesale orders from email and voicemail, enters them for the morning bake, and flags anything unusual.
Decisions needed from you: 1
Which orders should always go to a person rather than the agent?
The bake sheet hand-off is built around this. Without an answer, the trial week starts with every order checked by hand.
Needed by 13 Nov 2026
Time, work and spend
Work is ahead of the calendar: 64% done with 57% of the time gone.
Show as a table
| Measure | Share | Detail |
|---|---|---|
| Time elapsed | 57% | 56 of 98 days |
| Work done | 64% | 51 of 80 points |
| SOW spent | 50% | US$27,000 of US$54,000 |
| Hours used | 57% | 172 h of 302 h |
SOW estimate
US$54,000
Forecast to land at US$42,353
Spent to date
US$27,000
50% of the SOW estimate
Schedule
10 days ahead
Forecast 1 Dec 2026 · due 11 Dec 2026
Hours used
172 h
of 302 h planned
Change orders
- 4 Sept 2026 · SOW as signedUS$48,000
- 9 Oct 2026 · Flagging unusual orders for a person to check+US$6,000
- SOW estimate todayUS$54,000
What changed
- In the last week
- Work done
- 56% to 64%
- SOW spent
- 44% to 50%
- Hours used
- 50% to 57%
In the last week
- 29 Oct 2026 Finished: Turn voicemails into text
- 26 Oct 2026 Decision asked of you: Which orders should always go to a person rather than the agent?
What is next
- Enter voicemail orders the same way as email ones
- Handle voicemails that are hard to hear
- Agree which orders always go to a person
- Lay out the morning's bake sheet
Blocked
Nothing is blocked.
Earlier (20)
- 23 Oct 2026 Milestone reached: Product matching
- 22 Oct 2026 Finished: Sign off product matching with the team
- 20 Oct 2026 Finished: Show how well matching is doing on one page
- 15 Oct 2026 Finished: Flag unusual orders for a person to check
- 9 Oct 2026 Finished: Remember corrections, so a mistake only happens once
- 9 Oct 2026 Scope changed by 8 points: Flagging unusual orders for a person to check, asked for after the first review
- 9 Oct 2026 Change order: Flagging unusual orders for a person to check, US$6,000 added to the SOW estimate
- 8 Oct 2026 Finished: Test matching on last month's orders
- 8 Oct 2026 Decided: Should unusual orders be flagged for checking, at 8 more points of work? Yes, add it.
- 5 Oct 2026 Decision asked of you: Should unusual orders be flagged for checking, at 8 more points of work?
- 2 Oct 2026 Finished: Load the current product list
- 30 Sept 2026 Finished: Recognise products however customers name them
- 25 Sept 2026 Finished: Draft order entries for someone to check
- 25 Sept 2026 Milestone reached: Email orders
- 23 Sept 2026 Finished: Pull products and quantities out of an email
- 18 Sept 2026 Finished: Keep every order in one place for checking
- 16 Sept 2026 Finished: Read orders from the wholesale inbox
- 11 Sept 2026 Finished: Agree what a correct order looks like
- 11 Sept 2026 Milestone reached: Walkthrough
- 9 Sept 2026 Finished: Watch how orders come in today
Trends
- Actual
- Ideal pace
- SOW estimate
- Forecast at current pace
- Milestone
- Check-in
- 30 Oct
- Work left
- 29 points
- Spent
- US$27,000
- Hours left
- 130 h
Work
29 points of 80 left
Spend against the SOW
US$27,000 spent of the US$54,000 SOW estimate, with US$6,000 in change orders, forecast to land at US$42,353
Hours
130 h of 302 h left
Show as a table
| Check-in | Work left | Spent | Hours left |
|---|---|---|---|
| 4 Sept 2026 | 72 points | US$0 | 302 h |
| 11 Sept 2026 | 66 points | US$3,100 | 280 h |
| 18 Sept 2026 | 59 points | US$6,360 | 258 h |
| 25 Sept 2026 | 53 points | US$10,180 | 236 h |
| 2 Oct 2026 | 45 points | US$13,540 | 214 h |
| 9 Oct 2026 | 47 points | US$16,860 | 192 h |
| 16 Oct 2026 | 40 points | US$20,200 | 170 h |
| 23 Oct 2026 | 35 points | US$23,960 | 150 h |
| 30 Oct 2026 | 29 points | US$27,000 | 130 h |
The plan · next: Voicemail orders, 6 Nov 2026
- 1WalkthroughDone · 11 Sept 2026
- 2Email ordersDone · 25 Sept 2026
- 3Product matchingDone · 23 Oct 2026
- 4Voicemail ordersIn progress · 6 Nov 2026
- 5Bake sheet hand-offUpcoming · 27 Nov 2026
- 6Switch onUpcoming · 11 Dec 2026
Resources
Engineering
64 h
of 112 h planned
Automation and AI
70 h
of 114 h planned
Design
7 h
of 16 h planned
Project management
31 h
of 60 h planned
- Hours used
- Hours planned
- Sprint 1Engineering14 of 14 hAutomation and AI14 of 14 hDesign6 of 6 hProject management10 of 10 h
- Sprint 2Engineering16 of 16 hAutomation and AI20 of 20 hDesign1 of 2 hProject management7 of 8 h
- Sprint 3Engineering17 of 18 hAutomation and AI19 of 20 hDesignNone plannedProject management8 of 8 h
- Sprint 4Engineering17 of 18 hAutomation and AI17 of 18 hDesignNone plannedProject management6 of 6 h
- Sprint 5Engineering0 of 18 hAutomation and AI0 of 20 hDesign0 of 2 hProject management0 of 8 h
- Sprint 6Engineering0 of 16 hAutomation and AI0 of 14 hDesign0 of 4 hProject management0 of 8 h
- Sprint 7Engineering0 of 12 hAutomation and AI0 of 8 hDesign0 of 2 hProject management0 of 12 h
Materials
- AI model usageUS$480
- Speech-to-text trialUS$700
Show as a table
| Sprint | Engineering | Automation and AI | Design | Project management |
|---|---|---|---|---|
| Sprint 1 | 14 of 14 h | 14 of 14 h | 6 of 6 h | 10 of 10 h |
| Sprint 2 | 16 of 16 h | 20 of 20 h | 1 of 2 h | 7 of 8 h |
| Sprint 3 | 17 of 18 h | 19 of 20 h | 0 of 0 h | 8 of 8 h |
| Sprint 4 | 17 of 18 h | 17 of 18 h | 0 of 0 h | 6 of 6 h |
| Sprint 5 | 0 of 18 h | 0 of 20 h | 0 of 2 h | 0 of 8 h |
| Sprint 6 | 0 of 16 h | 0 of 14 h | 0 of 4 h | 0 of 8 h |
| Sprint 7 | 0 of 12 h | 0 of 8 h | 0 of 2 h | 0 of 12 h |