Ground Crew
← Your projects

Show report

As of 30 Oct 2026

Harbour Bakery

Wholesale order intake

Healthy

On track to finish 1 Dec 2026, 10 days early, and under the SOW estimate.

An agent that reads wholesale orders from email and voicemail, enters them for the morning bake, and flags anything unusual.

Decisions needed from you: 1

  • Which orders should always go to a person rather than the agent?

    The bake sheet hand-off is built around this. Without an answer, the trial week starts with every order checked by hand.

    Needed by 13 Nov 2026

Cue 01

Time, work and spend

Work is ahead of the calendar: 64% done with 57% of the time gone.

Time elapsed56 of 98 days
57%
Work done51 of 80 points
64%
SOW spentUS$27,000 of US$54,000
50%
Show as a table
MeasureShareDetail
Time elapsed57%56 of 98 days
Work done64%51 of 80 points
SOW spent50%US$27,000 of US$54,000
Hours used57%172 h of 302 h

SOW estimate

US$54,000

Forecast to land at US$42,353

Spent to date

US$27,000

50% of the SOW estimate

Schedule

10 days ahead

Forecast 1 Dec 2026 · due 11 Dec 2026

Hours used

172 h

of 302 h planned

Change orders

  • 4 Sept 2026 · SOW as signedUS$48,000
  • 9 Oct 2026 · Flagging unusual orders for a person to check+US$6,000
  • SOW estimate todayUS$54,000
Cue 02

What changed

In the last week
Work done
56% to 64%
SOW spent
44% to 50%
Hours used
50% to 57%

In the last week

  • 29 Oct 2026 Finished: Turn voicemails into text
  • 26 Oct 2026 Decision asked of you: Which orders should always go to a person rather than the agent?

What is next

  • Enter voicemail orders the same way as email ones
  • Handle voicemails that are hard to hear
  • Agree which orders always go to a person
  • Lay out the morning's bake sheet

Blocked

Nothing is blocked.

Earlier (20)
  • 23 Oct 2026 Milestone reached: Product matching
  • 22 Oct 2026 Finished: Sign off product matching with the team
  • 20 Oct 2026 Finished: Show how well matching is doing on one page
  • 15 Oct 2026 Finished: Flag unusual orders for a person to check
  • 9 Oct 2026 Finished: Remember corrections, so a mistake only happens once
  • 9 Oct 2026 Scope changed by 8 points: Flagging unusual orders for a person to check, asked for after the first review
  • 9 Oct 2026 Change order: Flagging unusual orders for a person to check, US$6,000 added to the SOW estimate
  • 8 Oct 2026 Finished: Test matching on last month's orders
  • 8 Oct 2026 Decided: Should unusual orders be flagged for checking, at 8 more points of work? Yes, add it.
  • 5 Oct 2026 Decision asked of you: Should unusual orders be flagged for checking, at 8 more points of work?
  • 2 Oct 2026 Finished: Load the current product list
  • 30 Sept 2026 Finished: Recognise products however customers name them
  • 25 Sept 2026 Finished: Draft order entries for someone to check
  • 25 Sept 2026 Milestone reached: Email orders
  • 23 Sept 2026 Finished: Pull products and quantities out of an email
  • 18 Sept 2026 Finished: Keep every order in one place for checking
  • 16 Sept 2026 Finished: Read orders from the wholesale inbox
  • 11 Sept 2026 Finished: Agree what a correct order looks like
  • 11 Sept 2026 Milestone reached: Walkthrough
  • 9 Sept 2026 Finished: Watch how orders come in today
Cue 03

Trends

  • Actual
  • Ideal pace
  • SOW estimate
  • Forecast at current pace
  • Milestone
Check-in
30 Oct
Work left
29 points
Spent
US$27,000
Hours left
130 h

Work

29 points of 80 left

020406080OctNovDecDueWalkthrough, 11 Sept 2026Email orders, 25 Sept 2026Product matching, 23 Oct 2026Voicemail orders, 6 Nov 2026Bake sheet hand-off, 27 Nov 2026Switch on, 11 Dec 20264 Sept 2026: 72 points left11 Sept 2026: 66 points left18 Sept 2026: 59 points left25 Sept 2026: 53 points left2 Oct 2026: 45 points left9 Oct 2026: 47 points left16 Oct 2026: 40 points left23 Oct 2026: 35 points left30 Oct 2026: 29 points left+8 added29 points leftToday

Spend against the SOW

US$27,000 spent of the US$54,000 SOW estimate, with US$6,000 in change orders, forecast to land at US$42,353

020k40k60kOctNovDecDueWalkthrough, 11 Sept 2026Email orders, 25 Sept 2026Product matching, 23 Oct 2026Voicemail orders, 6 Nov 2026Bake sheet hand-off, 27 Nov 2026Switch on, 11 Dec 20264 Sept 2026: US$0 spent11 Sept 2026: US$3,100 spent18 Sept 2026: US$6,360 spent25 Sept 2026: US$10,180 spent2 Oct 2026: US$13,540 spent9 Oct 2026: US$16,860 spent16 Oct 2026: US$20,200 spent23 Oct 2026: US$23,960 spent30 Oct 2026: US$27,000 spent+US$6,000 change orderUS$27,000 spentToday

Hours

130 h of 302 h left

0100200300400OctNovDecDueWalkthrough, 11 Sept 2026Email orders, 25 Sept 2026Product matching, 23 Oct 2026Voicemail orders, 6 Nov 2026Bake sheet hand-off, 27 Nov 2026Switch on, 11 Dec 20264 Sept 2026: 302 h left11 Sept 2026: 280 h left18 Sept 2026: 258 h left25 Sept 2026: 236 h left2 Oct 2026: 214 h left9 Oct 2026: 192 h left16 Oct 2026: 170 h left23 Oct 2026: 150 h left30 Oct 2026: 130 h left130 h leftToday
Show as a table
Check-inWork leftSpentHours left
4 Sept 202672 pointsUS$0302 h
11 Sept 202666 pointsUS$3,100280 h
18 Sept 202659 pointsUS$6,360258 h
25 Sept 202653 pointsUS$10,180236 h
2 Oct 202645 pointsUS$13,540214 h
9 Oct 202647 pointsUS$16,860192 h
16 Oct 202640 pointsUS$20,200170 h
23 Oct 202635 pointsUS$23,960150 h
30 Oct 202629 pointsUS$27,000130 h

The plan · next: Voicemail orders, 6 Nov 2026

  1. 1WalkthroughDone · 11 Sept 2026
  2. 2Email ordersDone · 25 Sept 2026
  3. 3Product matchingDone · 23 Oct 2026
  4. 4Voicemail ordersIn progress · 6 Nov 2026
  5. 5Bake sheet hand-offUpcoming · 27 Nov 2026
  6. 6Switch onUpcoming · 11 Dec 2026
Cue 04

Resources

Engineering

64 h

of 112 h planned

Automation and AI

70 h

of 114 h planned

Design

7 h

of 16 h planned

Project management

31 h

of 60 h planned

  • Hours used
  • Hours planned
  • Sprint 1
    Engineering
    14 of 14 h
    Automation and AI
    14 of 14 h
    Design
    6 of 6 h
    Project management
    10 of 10 h
  • Sprint 2
    Engineering
    16 of 16 h
    Automation and AI
    20 of 20 h
    Design
    1 of 2 h
    Project management
    7 of 8 h
  • Sprint 3
    Engineering
    17 of 18 h
    Automation and AI
    19 of 20 h
    Design
    None planned
    Project management
    8 of 8 h
  • Sprint 4
    Engineering
    17 of 18 h
    Automation and AI
    17 of 18 h
    Design
    None planned
    Project management
    6 of 6 h
  • Sprint 5
    Engineering
    0 of 18 h
    Automation and AI
    0 of 20 h
    Design
    0 of 2 h
    Project management
    0 of 8 h
  • Sprint 6
    Engineering
    0 of 16 h
    Automation and AI
    0 of 14 h
    Design
    0 of 4 h
    Project management
    0 of 8 h
  • Sprint 7
    Engineering
    0 of 12 h
    Automation and AI
    0 of 8 h
    Design
    0 of 2 h
    Project management
    0 of 12 h

Materials

  • AI model usageUS$480
  • Speech-to-text trialUS$700
Show as a table
SprintEngineeringAutomation and AIDesignProject management
Sprint 114 of 14 h14 of 14 h6 of 6 h10 of 10 h
Sprint 216 of 16 h20 of 20 h1 of 2 h7 of 8 h
Sprint 317 of 18 h19 of 20 h0 of 0 h8 of 8 h
Sprint 417 of 18 h17 of 18 h0 of 0 h6 of 6 h
Sprint 50 of 18 h0 of 20 h0 of 2 h0 of 8 h
Sprint 60 of 16 h0 of 14 h0 of 4 h0 of 8 h
Sprint 70 of 12 h0 of 8 h0 of 2 h0 of 12 h
Cue 05

Sprints and tasks

Loading…