As of 30 Oct 2026

Harbour Bakery

Stock reordering

Needs attention

Forecast to finish 4 Dec 2026, 7 days late, and about 4% over the SOW estimate.

Watches ingredient levels against upcoming orders and drafts supplier orders for approval each evening.

Decisions needed from you: 1

  • Who at the bakery can ask the flour supplier for access to its ordering system?

    Supplier ordering is waiting on this. Each week without access moves the switch-on by about a week.

    Needed by 4 Nov 2026

What needs attention: 2 things

  • Forecast to finish 7 days after the due date
  • Blocked for 4 days: Supplier has not granted access to its ordering system
Cue 01

Time, work and spend

Time, work and spend are within a few points of each other.

Time elapsed70 of 98 days
71%
Work done40 of 60 points
67%
SOW spentUS$25,000 of US$36,000
69%
Show as a table
MeasureShareDetail
Time elapsed71%70 of 98 days
Work done67%40 of 60 points
SOW spent69%US$25,000 of US$36,000
Hours used71%163 h of 228 h

SOW estimate

US$36,000

Forecast to land at US$37,500

Spent to date

US$25,000

69% of the SOW estimate

Schedule

7 days behind

Forecast 4 Dec 2026 · due 27 Nov 2026

Hours used

163 h

of 228 h planned

Cue 02

What changed

In the last week
Work done
60% to 67%
SOW spent
63% to 69%
Hours used
65% to 71%

In the last week

  • 28 Oct 2026 Finished: Draft a supplier order each evening
  • 26 Oct 2026 Blocked: Connect to the flour supplier's ordering system
  • 26 Oct 2026 Decision asked of you: Who at the bakery can ask the flour supplier for access to its ordering system?

What is next

  • Approve or change the evening's draft
  • Send the dairy order by email
  • Lay out the evening approval screen

Blocked

  • Supplier has not granted access to its ordering systemSince 26 Oct 2026
Earlier (14)
  • 23 Oct 2026 Finished: Sign off the forecast
  • 23 Oct 2026 Milestone reached: Usage forecast
  • 22 Oct 2026 Finished: Compare drafts with what the team would have ordered
  • 15 Oct 2026 Finished: Allow for deliveries already on their way
  • 8 Oct 2026 Finished: Forecast ingredients from upcoming orders
  • 1 Oct 2026 Finished: Sign off the stock levels page
  • 30 Sept 2026 Finished: Keep a history of stock levels
  • 29 Sept 2026 Finished: Work out how much each bake uses
  • 25 Sept 2026 Milestone reached: Stock levels
  • 17 Sept 2026 Finished: Spot counts that look wrong
  • 10 Sept 2026 Finished: Show ingredient levels in one place
  • 3 Sept 2026 Finished: Get daily stock counts from the till
  • 28 Aug 2026 Milestone reached: Walkthrough
  • 27 Aug 2026 Finished: Walk through how stock is ordered today
Cue 03

Trends

  • Actual
  • Ideal pace
  • SOW estimate
  • Forecast at current pace
  • Milestone
Check-in
30 Oct
Work left
20 points
Spent
US$25,000
Hours left
65 h

Work

20 points of 60 left

0204060SeptOctNovDecDueWalkthrough, 28 Aug 2026Stock levels, 25 Sept 2026Usage forecast, 23 Oct 2026Supplier ordering, 13 Nov 2026Switch on, 27 Nov 202621 Aug 2026: 60 points left28 Aug 2026: 57 points left4 Sept 2026: 55 points left11 Sept 2026: 52 points left18 Sept 2026: 49 points left25 Sept 2026: 46 points left2 Oct 2026: 40 points left9 Oct 2026: 35 points left16 Oct 2026: 30 points left23 Oct 2026: 24 points left30 Oct 2026: 20 points left20 points leftToday

Spend against the SOW

US$25,000 spent of the US$36,000 SOW estimate, forecast to land at US$37,500

010k20k30k40kSeptOctNovDecDueWalkthrough, 28 Aug 2026Stock levels, 25 Sept 2026Usage forecast, 23 Oct 2026Supplier ordering, 13 Nov 2026Switch on, 27 Nov 202621 Aug 2026: US$0 spent28 Aug 2026: US$2,120 spent4 Sept 2026: US$4,400 spent11 Sept 2026: US$6,590 spent18 Sept 2026: US$8,840 spent25 Sept 2026: US$11,820 spent2 Oct 2026: US$14,540 spent9 Oct 2026: US$17,090 spent16 Oct 2026: US$20,410 spent23 Oct 2026: US$22,810 spent30 Oct 2026: US$25,000 spentUS$25,000 spentToday

Hours

65 h of 228 h left

050100150200250SeptOctNovDecDueWalkthrough, 28 Aug 2026Stock levels, 25 Sept 2026Usage forecast, 23 Oct 2026Supplier ordering, 13 Nov 2026Switch on, 27 Nov 202621 Aug 2026: 228 h left28 Aug 2026: 212 h left4 Sept 2026: 196 h left11 Sept 2026: 181 h left18 Sept 2026: 166 h left25 Sept 2026: 149 h left2 Oct 2026: 131 h left9 Oct 2026: 114 h left16 Oct 2026: 96 h left23 Oct 2026: 80 h left30 Oct 2026: 65 h left65 h leftToday
Show as a table
Check-inWork leftSpentHours left
21 Aug 202660 pointsUS$0228 h
28 Aug 202657 pointsUS$2,120212 h
4 Sept 202655 pointsUS$4,400196 h
11 Sept 202652 pointsUS$6,590181 h
18 Sept 202649 pointsUS$8,840166 h
25 Sept 202646 pointsUS$11,820149 h
2 Oct 202640 pointsUS$14,540131 h
9 Oct 202635 pointsUS$17,090114 h
16 Oct 202630 pointsUS$20,41096 h
23 Oct 202624 pointsUS$22,81080 h
30 Oct 202620 pointsUS$25,00065 h

The plan · next: Supplier ordering, 13 Nov 2026

  1. 1WalkthroughDone · 28 Aug 2026
  2. 2Stock levelsDone · 25 Sept 2026
  3. 3Usage forecastDone · 23 Oct 2026
  4. 4Supplier orderingIn progress · 13 Nov 2026
  5. 5Switch onUpcoming · 27 Nov 2026
Cue 04

Resources

Engineering

67 h

of 92 h planned

Automation and AI

54 h

of 74 h planned

Design

6 h

of 8 h planned

Project management

36 h

of 54 h planned

  • Hours used
  • Hours planned
  • Sprint 1
    Engineering
    10 of 10 h
    Automation and AI
    6 of 6 h
    Design
    6 of 6 h
    Project management
    10 of 10 h
  • Sprint 2
    Engineering
    12 of 12 h
    Automation and AI
    11 of 10 h
    Design
    None planned
    Project management
    7 of 8 h
  • Sprint 3
    Engineering
    16 of 14 h
    Automation and AI
    13 of 12 h
    Design
    None planned
    Project management
    6 of 6 h
  • Sprint 4
    Engineering
    16 of 14 h
    Automation and AI
    13 of 12 h
    Design
    None planned
    Project management
    6 of 6 h
  • Sprint 5
    Engineering
    13 of 14 h
    Automation and AI
    11 of 12 h
    Design
    None planned
    Project management
    7 of 6 h
  • Sprint 6
    Engineering
    0 of 16 h
    Automation and AI
    0 of 12 h
    Design
    0 of 2 h
    Project management
    0 of 8 h
  • Sprint 7
    Engineering
    0 of 12 h
    Automation and AI
    0 of 10 h
    Design
    None planned
    Project management
    0 of 10 h

Materials

  • Supplier test environmentUS$430
  • AI model usageUS$600
Show as a table
SprintEngineeringAutomation and AIDesignProject management
Sprint 110 of 10 h6 of 6 h6 of 6 h10 of 10 h
Sprint 212 of 12 h11 of 10 h0 of 0 h7 of 8 h
Sprint 316 of 14 h13 of 12 h0 of 0 h6 of 6 h
Sprint 416 of 14 h13 of 12 h0 of 0 h6 of 6 h
Sprint 513 of 14 h11 of 12 h0 of 0 h7 of 6 h
Sprint 60 of 16 h0 of 12 h0 of 2 h0 of 8 h
Sprint 70 of 12 h0 of 10 h0 of 0 h0 of 10 h
Cue 05

Sprints and tasks

Loading…