As of 30 Oct 2026
Harbour Bakery
Stock reordering
Needs attentionForecast to finish 4 Dec 2026, 7 days late, and about 4% over the SOW estimate.
Watches ingredient levels against upcoming orders and drafts supplier orders for approval each evening.
Decisions needed from you: 1
Who at the bakery can ask the flour supplier for access to its ordering system?
Supplier ordering is waiting on this. Each week without access moves the switch-on by about a week.
Needed by 4 Nov 2026
What needs attention: 2 things
- Forecast to finish 7 days after the due date
- Blocked for 4 days: Supplier has not granted access to its ordering system
Time, work and spend
Time, work and spend are within a few points of each other.
Show as a table
| Measure | Share | Detail |
|---|---|---|
| Time elapsed | 71% | 70 of 98 days |
| Work done | 67% | 40 of 60 points |
| SOW spent | 69% | US$25,000 of US$36,000 |
| Hours used | 71% | 163 h of 228 h |
SOW estimate
US$36,000
Forecast to land at US$37,500
Spent to date
US$25,000
69% of the SOW estimate
Schedule
7 days behind
Forecast 4 Dec 2026 · due 27 Nov 2026
Hours used
163 h
of 228 h planned
What changed
- In the last week
- Work done
- 60% to 67%
- SOW spent
- 63% to 69%
- Hours used
- 65% to 71%
In the last week
- 28 Oct 2026 Finished: Draft a supplier order each evening
- 26 Oct 2026 Blocked: Connect to the flour supplier's ordering system
- 26 Oct 2026 Decision asked of you: Who at the bakery can ask the flour supplier for access to its ordering system?
What is next
- Approve or change the evening's draft
- Send the dairy order by email
- Lay out the evening approval screen
Blocked
- Supplier has not granted access to its ordering systemSince 26 Oct 2026
Earlier (14)
- 23 Oct 2026 Finished: Sign off the forecast
- 23 Oct 2026 Milestone reached: Usage forecast
- 22 Oct 2026 Finished: Compare drafts with what the team would have ordered
- 15 Oct 2026 Finished: Allow for deliveries already on their way
- 8 Oct 2026 Finished: Forecast ingredients from upcoming orders
- 1 Oct 2026 Finished: Sign off the stock levels page
- 30 Sept 2026 Finished: Keep a history of stock levels
- 29 Sept 2026 Finished: Work out how much each bake uses
- 25 Sept 2026 Milestone reached: Stock levels
- 17 Sept 2026 Finished: Spot counts that look wrong
- 10 Sept 2026 Finished: Show ingredient levels in one place
- 3 Sept 2026 Finished: Get daily stock counts from the till
- 28 Aug 2026 Milestone reached: Walkthrough
- 27 Aug 2026 Finished: Walk through how stock is ordered today
Trends
- Actual
- Ideal pace
- SOW estimate
- Forecast at current pace
- Milestone
- Check-in
- 30 Oct
- Work left
- 20 points
- Spent
- US$25,000
- Hours left
- 65 h
Work
20 points of 60 left
Spend against the SOW
US$25,000 spent of the US$36,000 SOW estimate, forecast to land at US$37,500
Hours
65 h of 228 h left
Show as a table
| Check-in | Work left | Spent | Hours left |
|---|---|---|---|
| 21 Aug 2026 | 60 points | US$0 | 228 h |
| 28 Aug 2026 | 57 points | US$2,120 | 212 h |
| 4 Sept 2026 | 55 points | US$4,400 | 196 h |
| 11 Sept 2026 | 52 points | US$6,590 | 181 h |
| 18 Sept 2026 | 49 points | US$8,840 | 166 h |
| 25 Sept 2026 | 46 points | US$11,820 | 149 h |
| 2 Oct 2026 | 40 points | US$14,540 | 131 h |
| 9 Oct 2026 | 35 points | US$17,090 | 114 h |
| 16 Oct 2026 | 30 points | US$20,410 | 96 h |
| 23 Oct 2026 | 24 points | US$22,810 | 80 h |
| 30 Oct 2026 | 20 points | US$25,000 | 65 h |
The plan · next: Supplier ordering, 13 Nov 2026
- 1WalkthroughDone · 28 Aug 2026
- 2Stock levelsDone · 25 Sept 2026
- 3Usage forecastDone · 23 Oct 2026
- 4Supplier orderingIn progress · 13 Nov 2026
- 5Switch onUpcoming · 27 Nov 2026
Resources
Engineering
67 h
of 92 h planned
Automation and AI
54 h
of 74 h planned
Design
6 h
of 8 h planned
Project management
36 h
of 54 h planned
- Hours used
- Hours planned
- Sprint 1Engineering10 of 10 hAutomation and AI6 of 6 hDesign6 of 6 hProject management10 of 10 h
- Sprint 2Engineering12 of 12 hAutomation and AI11 of 10 hDesignNone plannedProject management7 of 8 h
- Sprint 3Engineering16 of 14 hAutomation and AI13 of 12 hDesignNone plannedProject management6 of 6 h
- Sprint 4Engineering16 of 14 hAutomation and AI13 of 12 hDesignNone plannedProject management6 of 6 h
- Sprint 5Engineering13 of 14 hAutomation and AI11 of 12 hDesignNone plannedProject management7 of 6 h
- Sprint 6Engineering0 of 16 hAutomation and AI0 of 12 hDesign0 of 2 hProject management0 of 8 h
- Sprint 7Engineering0 of 12 hAutomation and AI0 of 10 hDesignNone plannedProject management0 of 10 h
Materials
- Supplier test environmentUS$430
- AI model usageUS$600
Show as a table
| Sprint | Engineering | Automation and AI | Design | Project management |
|---|---|---|---|---|
| Sprint 1 | 10 of 10 h | 6 of 6 h | 6 of 6 h | 10 of 10 h |
| Sprint 2 | 12 of 12 h | 11 of 10 h | 0 of 0 h | 7 of 8 h |
| Sprint 3 | 16 of 14 h | 13 of 12 h | 0 of 0 h | 6 of 6 h |
| Sprint 4 | 16 of 14 h | 13 of 12 h | 0 of 0 h | 6 of 6 h |
| Sprint 5 | 13 of 14 h | 11 of 12 h | 0 of 0 h | 7 of 6 h |
| Sprint 6 | 0 of 16 h | 0 of 12 h | 0 of 2 h | 0 of 8 h |
| Sprint 7 | 0 of 12 h | 0 of 10 h | 0 of 0 h | 0 of 10 h |